Photo: Lorem Ipsum

Street Restoration Work to Begin Monday, July 30

Friday, July 27, 2012

On Monday, July 30, 2012, Chevy Chase Village contract paving crews will begin to repair and fully restore the roadways affected by WSSC's recently completed water main replacement project. As part of these restoration efforts, the Village's contractor will be grinding away the existing asphalt surface in preparation for new asphalt. Full restoration of the two (2) miles of roadway affected by the water main replacement, is scheduled to be completed by Friday, August 10, weather permitting.

During work hours, parking will be restricted on the affected streets. If necessary, the Village Police Department will arrange and supervise the towing of parked cars to nearby unaffected streets. While the Village and its paving contractor will work to keep the roadway open as much as possible, temporary closures might be required during the asphalt grinding process. All traffic will be restricted once the fresh asphalt is being applied and until it cools. Once the roadway is safe for traffic the Village's paving contractor will re-open the roadway.

In order to assist the Village's paving contractor, residents are asked to please avoid driving on the affected streets during the scheduled days outlined below. Please note that this schedule is subject to change due to weather or other construction related delays. If an adjustment is required, the schedule will be updated accordingly.

Nevada Avenue (between East Lenox
Street and East Melrose Street)
Complete
East Melrose Circle Complete
Oxford Street (between Broad Branch Road
and the Village of Martin’s Additions)
Complete
Asphalt Patch Primrose St. at Brookville Rd. Complete
Broad Branch Road Complete
East Irving Street (between Connecticut
Avenue and Brookville Road)
Complete
East Kirke Street Thursday, August 2 – Friday, August 3
Oliver Street Friday, August 3 – Tuesday, August 7
Cedar Parkway (between West Lenox
Street and Center Street)
Tuesday, August 7 – Thursday, August 9
Dead-end of West Lenox Street Tuesday, August 7 – Thursday, August 9
West Kirke Street (odd side between Magnolia
Parkway and Connecticut Avenue)
Wednesday, August 8 – Thursday, August 9
Asphalt Patch Magnolia Parkway at
West Kirke Street
Thursday, August 9

 

We thank you in advance for your assistance and patience during this project. Should you have any questions or concerns, please contact the Village office at (301) 654-7300.